Dudgeon nears halfway

A2Sea has installed 28 of the 67 Siemens turbines at 402MW project




Dudgeon nears halfway  image



A2Sea jack-up Sea Challenger has installed 28 of the 67 Siemens 6MW turbines for Statoil’s 402MW Dudgeon offshore wind farm off the coast of Norfolk. 

The vessel is currently installing its latest cargo of four turbines at the site, which when completed will edge construction towards the halfway point.  

Eighteen of the installed turbines have been fully commissioned and handed over to Statoil. Commissioning work will continue until into the fourth quarter of this year.

Scour protection will also be added to each of the wind farm’s monopile foundations this month.

The scour work will be led by Van Oord side stone dumping vessel Ham 601, and is expected to last until mid-June. 

Image: A2Sea













Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s